Sq. Ft. = 79,000 | Year = 2000-2001, 2003, 2004 | Total Cost = Rs. 653 Lacs
M/s Archivista Consultants, Pune
The first phase of the construction included the main plant utility building covered with RCC grid slab at 5.20 mtrs. height. The main plant had forced air ventilation systems, air compressor pipe lines, powder coating yard with a HDPE drainage system.
The second phase of the project included the construction of a main dye casting plant measuring 1150 Sqm.
The canteen building measures 440 sq. mtrs. and has a RCC frame structure covered with RCC slab at 5.0 m height.
The fourth phase is a steel structure that has a mezzanine floor, clean room and laboratory.